26.3 Nature of cumulative impacts
The assessment of potential cumulative impacts of the project has considered major developments that are proposed, have been approved (but not yet constructed), and/or would be constructed or operated at the same time as the planning, construction or operation of the M4-M5 Link project. Cumulative impacts are considered important to assess because in isolation, a particular impact from one project may be considered minor, but when the impact of multiple projects are considered, the impacts may be more substantial.
Impacts can be either adverse or beneficial. Where an adverse impact is considered likely, mitigation and/or management measures would be implemented to avoid or reduce those impacts. This chapter assumes that the specific mitigation and management measures outlined for the project in the various chapters of this environmental impact statement (EIS) have been applied and therefore focuses on the more strategic measures that may be implemented in coordination with other relevant projects. Project benefits, including the benefits of the overall WestConnex program of works, are discussed in Chapter 3 (Strategic context and project need).
26.3.1 Construction phase cumulative impacts
Cumulative impacts arise through spatial proximity (ie how close one project might be to another) as well as temporal proximity (ie projects that occur in a similar timeframe or have overlapping schedules). This assessment defines these interactions as concurrent (simultaneous) or consecutive (back-to-back) project activities. Ancillary activities refer to works by utility and service providers to provide new or relocated utilities (such as electricity, telecommunications, water and sewage connections). These activities have been considered and assessed in the EIS (refer to Appendix F (Utilities Management Strategy) for further details). These works may also lead to local traffic disruptions, restrictions to access, noise and vibration impacts, potential dust generation and reduced
visual amenity.
Indicative programs for construction of the various M4-M5 Link project components and construction ancillary facilities are outlined in Chapter 6 (Construction work). These have been considered by the various technical specialists and incorporated into the technical working papers of this EIS, with the outcomes presented in the technical assessment chapters of the EIS (Chapter 8 to Chapter 27). Final construction scheduling would be subject to the appointment of the successful construction contractor(s).
A consequence of concurrent or consecutive activities occurring over extended periods of time is the concept of construction fatigue. Construction fatigue can be experienced by receivers that are in the vicinity of concurrent or consecutive project construction activities where the activities overlap or have little or no break between the activities of one project, or multiple adjacent projects.
This cumulative impact assessment identifies three specific geographic areas where construction fatigue from concurrent or consecutive activities is likely to be experienced. These geographic areas are Haberfield/Ashfield, Rozelle and St Peters. Figure 26-2, Figure 26-3 and Figure 26-4 show these areas and the spatial and temporal overlap with other projects considered. The relevant projects withconcurrent or consecutive construction timeframes is presented in Table 26-2.
Table 26-2 Projects that may result in construction fatigue with the M4-M5 Link project
26.3.2 Operational phase cumulative impacts
As described in Appendix C (Cumulative impact assessment methodology), a number of strategic projects or land use/urban developments are already captured in the operational traffic modelling informing the cumulative operational assessments for traffic, air quality, noise and vibration, human health risk and social and economic environment and are therefore not discussed in detail in this
chapter.
The traffic assessment included modelling of cumulative operational traffic scenarios at 2023 (year of opening) and 2033 (ten years after opening). The modelling predicted traffic from the operation of the approved WestConnex projects and the M4-M5 Link as well as a number of proposed motorway projects, as shown in Table 26-3.
The traffic modelling was based on land use and employment forecasts for metropolitan Sydney including forecasts for proposed growth precincts such as the Parramatta Road corridor, Bays Precinct, Central to Eveleigh corridor, Green Square and Mascot town centre. The modelling also included a range of approved and proposed major road and public transport projects including CSELR and Sydney Metro City and Southwest. It also included forecast growth in the Sydney Airport and Port Botany precinct and the Western Sydney Airport at Badgerys Creek.
The cumulative assessment for the quantitative modelling scenarios has been discussed in detail in their respective assessments, such as traffic and transport (Appendix H (Technical working paper: Traffic and transport)), air quality (Appendix I (Technical working paper: Air quality)) and noise and vibration (Appendix J (Technical working paper: Noise and vibration)). This chapter only provides a summary of the key outcomes of the operational cumulative impact assessment.
Table 26-3 Cumulative operational scenarios as defined for the traffic, air quality, noise and human health assessments
26.3.3 Type of assessment
Depending on the environmental issue, the type of assessment undertaken in this EIS could be quantitative (such as predictive through modelling), qualitative, or a combination of both. The projects included in the cumulative impact assessment have been evaluated by technical specialists for the relevant key issues as identified in Table 26-1.
As described in Appendix C (Cumulative impact assessment methodology), a number of strategic projects (such as Western Sydney Airport) or land use/urban developments are already captured in the operational traffic modelling informing the cumulative operational assessments for traffic, air quality and noise and vibration and are therefore not discussed in detail in this chapter.
In accordance with the Secretary’s Environmental Assessment Requirements (SEARs) for the M4-M5 Link project, all key issues have been considered for the approved WestConnex component projects. This is to provide a cumulative impact assessment of the WestConnex program of works to date.
In some cases projects are in the early stages of design development and an EIS has not been prepared. In these cases, reasonable assumptions have been made in assessing potential cumulative impacts and these will need to be confirmed during the EIS assessments for these projects based on available information at that time. In the case of the proposed future Sydney Gateway project, the assumption is that the same design will be assessed as was assessed in the New M5 EIS.
26.4 Assessment of potential cumulative impacts
26.4.1 Traffic and transport
The cumulative traffic and transport assessment examines construction and operational traffic generation for future scenarios and capacity of the road network to manage the predicted changes in traffic volumes, as well as the impact on public and active transport. A detailed assessment of the potential construction and operational cumulative impacts is provided in Appendix H (Technical working paper: Traffic and transport).
Construction
Establishment of construction-based ancillary facilities for the project is associated with heavy and light vehicle movements, but only some of these sites (ie the tunnelling sites) would have heavy vehicle movements associated with spoil haulage. The traffic modelling for the cumulative construction assessment was undertaken for the year 2021, as it is considered to be the highest traffic-generating year of construction and therefore assesses the worst case construction traffic scenario.
The construction of the M4 East and New M5 projects are expected to be completed in 2019 and 2020. Therefore there would be an overlap with the construction of the M4-M5 Link project for a period of up to 12-18 months, subject to project approval. During this period of overlaptunnelling construction, the largest generator of heavy vehicle traffic, is unlikely to cause a substantial cumulative impact in terms of additional heavy vehicles on the road network from these three projects being under construction concurrently.
Elements of the construction program for the M4-M5 Link are assumed to occur concurrently with the construction of proposed future Sydney Gateway project, with both projects scheduled for completion in 2023. The EIS for the proposed future Sydney Gateway project would need to consider the cumulative impacts with the M4-M5 Link construction.
The construction of the proposed future Western Harbour Tunnel is assumed to overlap with the M4-M5 Link construction and the likely trip generation for heavy and light vehicles has been added to the cumulative construction assessment presented in this EIS.
Analysis indicates that the impact from additional Western Harbour Tunnel construction traffic on the road network is minimal, with most intersections operating at the same level of service (LoS). A few intersections along Wattle Street and Parramatta Road are forecast to experience a slight worsening in level of service during the AM and PM peak periods as a result of construction traffic, namely:
- Parramatta Road/Wattle Street intersection in the AM peak hour
- Parramatta Road/Harris Road and Parramatta Road/Croydon Road/Arlington Street intersections in the AM peak hour
- Wattle Street/Ramsay Street in the PM peak hour.
These cumulative impacts on the operation of the road network would not be experienced for the duration of the construction period and would be subject to further assessment in the Western Harbour Tunnel EIS.
Elements of the M4-M5 Link construction program would also occur concurrently with the construction of the Sydney Metro City and Southwest project (Stage 1: Chatswood to Sydenham). Construction traffic from the Sydney Metro Marrickville dive site, which is some distance to the west, may use the Princes Highway, which would also be used by traffic from the M4-M5 Link construction site at Campbell Road.
Site management works would occur within the Rozelle Rail Yards before the commencement of construction of the M4-M5 Link. Site management works have commenced, with completion planned for mid-2018. Due to the timing of works, there would be no concurrent traffic impacts with the M4-M5 Link. However, as the works would occur consecutively (ie back-to-back), residents in the vicinity would
experience traffic impacts from both projects being undertaken consecutively.
Impacts on public and active transport
On-road public transport in the cumulative construction scenario would generally experience levels of service as they do under the project construction scenario with a small reduction in levels of service in some locations due to the increased demand generated by the Western Harbour Tunnel construction traffic (which would be subject to a separate EIS ).
The potential impacts on pedestrians and cyclists at the Rozelle civil and tunnel site, potentially in the form of additional light vehicle movements along Lilyfield Road, would likely be lengthened due to the construction of the proposed future Western Harbour Tunnel.
Operation
Potential cumulative operational traffic impacts for 2023 and 2023 are summarised in Table 26-4.
While the construction impact of the proposed future Western Harbour Tunnel and Beaches Link entry and exit ramps connecting to City West Link/The Crescent is assessed, the operational traffic impact of these ramps has not been included. A preliminary assessment with these ramps operational has been carried out and indicates that there is likely to be some reduction in traffic on the Western Distributor and Sydney Harbour Bridge, as more traffic would be able to access the proposed future Western Harbour Tunnel and Beaches Link. However, there is likely to be increased traffic on City West Link, The Crescent and Johnston Street. The impacts of these entry and exit ramps would be assessed in detail as part of future environmental assessment for the proposed future Western Harbour Tunnel and Beaches Link.
Table 26-4 Cumulative operational traffic impacts (2023 and 2033)
M4-M5 Link Mainline tunnels
Compared to the 2023 ‘with project’ scenario, the 2023 ‘cumulative’ scenario analysis indicates traffic volumes on the M4- M5 Link mainline tunnels are forecast to generally be denser with a corresponding reduction in level of service (LoS) in the peak hours. However, the M4-M5 Link Motorway are still forecast to generally operate at LoS D or better.
The 2033 ‘cumulative’ scenario analysis indicates forecast traffic flows on the M4-M5 Link mainline tunnels would be denser compared to the 2033 ‘with project’ scenario, with a corresponding reduction in level of service in the peak hours. Sections of the M4-
M5 Link mainline tunnels are forecast to operate at LoS E in peak hours, particularly around the merge and diverge locations, such as where the Wattle Street interchange ramps connect with the M4-M5 Link mainline tunnels. Even with this increased density, average motorway speeds are forecast to be 60 km/h or above in the peak hours.
Metropolitan network efficiency
The metropolitan road network productivity improves in 2023, with the inclusion of the proposed future Sydney Gateway and Western Harbour Tunnel. There is a drop in the daily vehicle kilometres travelled (VKT) and vehicle hours travelled (VHT) on the arterial network with an increase in kilometres travelled along the motorway routes, a greater distance could be travelled on the road network in a shorter time.
Metropolitan road network productivity improves in 2033, with the inclusion of the proposed future Sydney Gateway, Western Harbour Tunnel and Beaches Link and the F6 Extension projects. There is a drop in the daily VKT and VHT on the arterial network with an increase in kilometres travelled along the motorway routes. As in 2023, overall, a greater distance could be travelled on the road network in a shorter time.
Parallel routes analysis
See description for 2033.
As a result of the additional road network capacity provided by the project, traffic volumes on parallel routes compared to a ‘without project’ scenario is predicted to significantly decrease on:
- City West Link and Parramatta Road, east of the M4 East
- Stanmore Road in Stanmore
- Lyons Road in Russell Lea
- Southern Cross Drive and the Sydney Harbour Tunnel.
The M4-M5 Link would provide alternative parallel options to the roads listed above together with the proposed future Sydney Gateway, Western Harbour Tunnel and Beaches Link and the F6 Extension in the 2023 and 2033 ‘cumulative’ scenarios. A decrease in the daily volume of heavy vehicles on surface roads such as Parramatta Road, City West Link, Stanmore Road, Sydenham Road, Marrickville Road and King Street is also forecast, as heavy vehicles shift onto the M4-M5 Link and the other motorways included in the ‘cumulative’ scenarios.
In the 2033 ‘cumulative’ scenario, increases are forecast in daily twoway volumes on Johnston Street, north of Parramatta Road in Annandale and Gladesville Bridge in the ‘cumulative’ scenario. These increases reflect the forecast demand to and from the Rozelle area due to the new connectivity being provided by the Rozelle
interchange.
Metropolitan travel time
See description for 2033.
In the 2023 and 2033 cumulative scenarios, peak period travel times are forecast to further reduce, by comparison to a ‘with project’ scenario, on a number of key travel routes such as between the M4 corridor and the Sydney Airport/Port Botany precinct. This is as a result of traffic shifting from surface roads to the M4-M5 Link and the other motorways included in the ‘cumulative’ scenarios.
Wattle Street interchange
The 2023 AM peak hour ‘cumulative’ conditions are forecast to be similar to those for the ‘with project’ scenario, with the main cause of congestion remaining the forecast demand for City West Link. There would be an increase in average speed on the modelled road network due to the higher proportion of vehicles using the M4-M5 Link in the ‘cumulative’ scenario.
The 2023 PM peak hour ‘cumulative’ conditions are forecast to be similar to those for the ‘with project’ scenario, with the main cause of congestion remaining the forecast demand to Frederick Street. As in the ‘with project’ scenario, significant queues are forecast on the Parramatta Road eastbound approach to Wattle Street and on Wattle Street itself. There would be an increase in average speed on the modelled road network due to the higher proportion of vehicles using the M4-M5 Link in the ‘cumulative’ scenario.
Performance across the majority of the modelled road network is consistent between ‘with project’ and ‘cumulative’ scenarios, with intersections performing at the same or better levels of service.
During the 2033 AM peak hour, the ‘cumulative’ scenario is forecast to experience a minor increase in overall average speed due to a forecast increased demand for the M4-M5 Link mainline tunnels when compared to the ‘with project’ scenario. Congestion on Wattle Street/Dobroyd Parade would impact motorists approaching the Wattle Street interchange from side roads – this would be experienced in both ‘with project’ and ‘cumulative’ scenarios.
The 2033 PM peak hour ‘cumulative’ conditions are forecast to be similar to those for the ‘with project’ scenario, with the forecast demand for Frederick Street remaining the main cause of congestion.
Performance across the majority of the modelled road network would be consistent between ‘with project’ and ‘cumulative’ scenarios, with intersections performing at the same or better levels of service.
Rozelle interchange
During the 2023 AM peak hour, an increase in demand is forecast for the ‘cumulative’ scenario over the ‘with project’ scenario. In spite of this increase, the ‘cumulative’ network would provide benefits to the Western Distributor and Anzac Bridge operation as traffic is forecast to shift from the Sydney Harbour Bridge to the proposed future Western Harbour Tunnel,
During the 2023 PM peak hour, the forecast demand for the ‘cumulative’ scenario increases by about 10 per cent over the ‘with project’ scenario. In spite of this increase, the modelled network is forecast to operate better than in the ‘cumulative’ case. Again, this is due to traffic being forecast to shift from the Sydney Harbour Bridge to the proposed future Western Harbour Tunnel.
The forecast intersection performances in the 2023 ‘cumulative’ scenario are similar to the ‘with project’ scenario.
As in 2023, the 2033 ‘cumulative’ scenario provides some benefit to the Western Distributor and Anzac Bridge, due to the forecast shift in traffic from the Anzac Bridge and Sydney Harbour Bridge to the proposed future Western Harbour Tunnel. This reassignment results in better flow for northbound traffic on Western Distributor towards Sydney Harbour Bridge with improved network performance.
As in 2023, the 2033 ‘cumulative’ network is forecast to perform better compared to the ‘with project’ case, despite a 15 per cent increase in forecast demand, due to the shift in traffic from the Sydney Harbour Bridge to the proposed future Western Harbour
Tunnel.
The forecast intersection performances in the 2033 ‘cumulative’ scenario are similar to the ‘with project’ scenario.
St Peters interchange
The AM peak hour network performance results in the 2023 cumulative scenario show overall improvement compared to the 2023 ‘with project’ scenario. Despite the higher forecast total demand, total travel time is shorter, indicating less congestion in the modelled network around the St Peters interchange. This is due to the proposed future Sydney Gateway improving connectivity between St Peters interchange and Sydney Airport precinct, removing traffic from the Mascot area. The PM peak
hour network performance results show a similar trend to the AM
peak hour.
Many intersections in the modelled road network are forecast to operate at similar or better levels of service, due to the contribution of the proposed future Sydney Gateway.
In the 2033 AM peak hour, the modelled network is forecast to operate better than the ’with project’ scenario, although not as significant an improvement as in 2023 due to the growth in traffic across the modelled network. Total forecast demand is higher than in the ‘with project’ scenario, however more vehicles are forecast to reach their destination, indicating less congestion than under the ‘with project’ scenario. This is due to the proposed future Sydney Gateway improving connectivity between St Peters interchange and the Sydney Airport precinct, removing traffic from the Mascot area.
The 2033 PM peak hour network performance results show improved network operation in the ‘cumulative’ scenario compared to the ‘with project’ scenario. Total travel time in the modelled road network is forecast to be shorter, with a doubling in average speed
on the network.
Many intersections within the modelled road network are forecast to operate at similar or better levels of service when compared to the ‘with project’ scenario, due to the contribution of the proposed future Sydney Gateway.
Public transport
Potential impacts to public transport in the cumulative scenarios are generally similar to the general traffic network performance assessments. On-road public transport would experience similar levels of service as they do under the ‘with project’ scenarios with a reduction in levels of service in some locations, due to the increased demand generated by the cumulative projects, and improvements in other locations, where the ‘cumulative’ network provides benefits to the surface road network.
Active transport
Positive cumulative impacts on active transport include the upgrade, extension and connectivity of pedestrian and cycle routes linking areas of public open space as a result of the combined suite of projects included in this cumulative assessment. This is presented in the active transport strategy presented in Appendix N (Technical working paper: Active transport strategy).
26.4.2 Air quality
The cumulative impact assessment for air quality focuses on the cumulative change in airborne pollutants as a result of the construction and operation of the M4-M5 Link project in combination with the other relevant projects presented in Table 26-1..
WestConnex projects
Construction
For all construction activities, a key aim is to prevent significant effects on receptors through the use of effective mitigation as described in section 26.3.1. There are three geographic locations that will experience a degree of combined construction impacts from multiple projects, these are at Haberfield, Rozelle and St Peters, which are each located within proximity to sensitive receivers.
These overlapping areas may experience extended periods of construction on a site-by-site and activity-by-activity basis. Irrespective of the duration, the generation of dust, which may cause amenity impacts to the surrounding community, can be effectively controlled. Air quality impacts from the activities expected during construction are manageable through well established and effective management and mitigation measures. Cumulative air quality impacts during construction are therefore not expected to be significant.
Operation
The operational component of the air quality assessment examines both in-tunnel air quality as well as surface ambient air quality and the changes under different operational scenarios and is reported on in Appendix I (Technical working paper: Air quality).
The project ventilation system is designed for coordinated operation with adjacent tunnel projects (ie the WestConnex M4 East and New M5 projects and the proposed future Western Harbour Tunnel and Beaches Link project), with complete or partial air exchange at project boundaries when necessary to ensure in-tunnel air quality is maintained throughout the tunnel network. The ventilation system is designed to have complete exchange of tunnel air between the proposed future Western Harbour
Tunnel and Beaches Link project and the M4-M5 Link project at the Rozelle ventilation facility.
For in-tunnel air quality, the project would meet the in-tunnel criterion for nitrogen dioxide (NO2) as an average concentration along any route through the tunnel network, and irrespective of contributions from other tunnel projects, therefore cumulative impacts on NO2 emissions are not relevant.
For ambient air quality, the air quality assessment uses changes in background air quality over time, plus surface traffic flows and emissions from ventilation outlets as key contributors to changes in air quality within and around the project footprint. The assessment presents each of the pollutants in the air quality assessment and uses the ‘residential, workplace and recreational (RWR) receptors’ as locations to measure the change. The RWR represent 86,375 individual receptors across the modelled network.
The sections below summarise the key findings of the assessment for the ‘Do something’ (DS) and ‘Do something cumulative’ (DSC) scenarios as compared with the ‘Do minimum’ (DM) scenario (ie without the project).
Table 26-5 Cumulative operational air quality impacts (2023 and 2033)
Carbon monoxide (CO) 1-hour concentration
The one-hour CO criterion for NSW was not exceeded at any of the RWR receptors in any scenario. The highest one-hour concentrations in any DS or DSC scenario was predicted to be 7.7 mg/m3 as compared to the criterion of 30 mg/m3.
NO2 annual mean
The annual mean NO2 criterion for NSW of 62 µg/m3 was not exceeded at any of the RWR receptors in the DSC scenario. Only around 0.1 per cent of receptors were predicted to have an increase of greater than 2 µg/m3 and there was a reduction in annual mean NO2 at between or around 80 per cent and 85 per cent of receptors, providing a benefit to the majority of receptors.
NO2 maximum 1- hour mean
The maximum one-hour mean NO2 concentration was predicted to be exceeded by 3.8 per cent of the RWR receptors in 2023 and less than 1 per cent in the 2033 DSC scenarios. These are compared to the DM scenario where 6.6 per cent of the RWR were predicted to experience an exceedance in 2023 and 2.3 per cent in 2033.
Particulate matter (PM10 annual mean)
The concentration at the majority of receptors was below 20 µg/m3, with only a very small proportion of receptors having a concentration exceeding the criterion of 25 µg/m3. The 2023 DS predicted 26.5 µg/m3 while the 2023 DSC scenario was
marginally less at 25.9 µg/m3. For the 2033 DS, the predicted maximum was 26.1
µg/m3 while for the 2033 DSC, it was marginally less at 25.8 µg/m3.
Particulate matter (PM10 24-hour mean)
The predicted results for the DSC scenarios were significantly influenced by the high PM10 background concentration of about 93 per cent of the criterion for 2023 and 2033. PM10 24 hour mean concentrations at the majority of RWR receptors was above the NSW impact assessment criterion of 50 µg/m3 both with and without the project.
Particulate matter (PM2.5 annual mean)
Similar to the PM10 pollutant, the PM2.5 background concentration is already very high and at most RWR receptors is close to the NSW criterion of 8 µg/m3. For the 2023 DSC scenario there is a maximum increase of 2.2 µg/m3 compared to 1.2 µg/m3 for the 2023 DS scenario. For the 2033 DSC scenario there is a maximum increase of 2.3 µg/m3
compared to 1.4 µg/m3 for the 2033 DS scenario. The predicted maximum values for the decrease in PM2.5 annual mean concentrations is similar for the DS and DSC scenarios for both 2023 and 2033.
Particulate matter (24-hour mean PM2.5)
Similar to 24-hour mean PM10, as a result of the high background levels, the concentrations predicted at all receptors was above the NSW impact assessment criterion of 25 µg/m3 for 24 hour mean PM2.5 concentrations. Again with the DSC
scenarios predicting marginally lower concentrations than the DS scenario for the
same year.
Regional air quality
The changes in the total emissions resulting from the project are shown in Table 26-6. These changes can be viewed as a proxy for the projects and the cumulative scenario’s impact on regional air quality which, on the basis of the results, are likely to be negligible. The graphs show minimal change between the DM, DS and DSC scenarios and all are significantly lower than the ‘Base Year (2015)’ emissions without any of the projects assessed in the DS or DSC in operation. For example:
- The increases in the oxides of nitrogen (NOX) emissions for the assessed road network in a given year ranged from 71 to 174 tonnes per year. These values equate to a very small proportion (around 0.3 per cent) of anthropogenic NOX emissions in the Sydney airshed in 2016 (around 53,700 tonnes)
- The increases in NOX in a given year are much smaller than the projected reductions in emissions between 2015 and 2033 (around 2,340 tonnes per year).
Overall, it is concluded that the cumulative impacts on regional air quality would be negligible, and undetectable in ambient air quality measurements at background locations.
26.4.3 Noise and vibration
An assessment of the potential construction and operational impact of the M4-M5 Link is provided in Chapter 10 (Noise and vibration) and is detailed in Appendix J (Technical working paper: Noise and vibration).
Construction
Cumulative construction noise impacts can be divided into two groups:
- Concurrent noise impacts, where more than one work activity is carried out at the same time and in the same location, such that the same receiver is potentially impacted. Concurrent construction noise impacts include construction civil and tunnelling sites which may operate simultaneously during any period. These construction areas are anticipated to include relatively stationary noise sources which operate for the majority of the construction period
- Consecutive noise impacts, where receivers are exposed to construction noise impacts from the construction of separate and consecutive nearby projects. Generally construction noise impact assessments consider the duration of a project in isolation, whereas the potential impacts from the identified consecutive projects are likely to be perceived to be longer by affected receivers.
Appendix J (Technical working paper: Noise and vibration) includes an assessment of concurrent construction impacts for each of the M4-M5 Link construction sites along with an assessment of consecutive impacts where approved or currently under construction projects occur within close proximity to an M4-M5 link project site. The following section provides discussion for sites where both consecutive and current construction impacts are predicted to occur.
Table 26-6 Cumulative operational noise impacts
Cumulative construction noise impacts – Haberfield Option A
Given the number of work sites associated with the project within the Haberfield area, it is likely that receivers would occasionally be subject to potential noise impacts from concurrent activities.
This would most likely be apparent during the night-time period where predicted noise
levels may exceed the noise management level (NML) by up to 10 dBA.
The M4 East project, together with the M4-M5 Link, tie in to Wattle Street at Haberfield, where receivers would likely be exposed to extended impacts associated with the consecutive construction of both projects. The receivers most likely to be affected by consecutive construction impacts are:
- Receivers adjoining the Northcote Street civil site (C3a). This site is currently a tunnel site for the M4 East project, with an acoustic shed constructed across the site
- Receivers adjoining Wattle Street and Walker Avenue, which have line of sight to the Wattle Street civil and tunnel site (C1a) and the Haberfield civil and tunnel site (C2a).
Cumulative construction noise impacts – Haberfield/Ashfield Option B
As above, due to the number of construction sites in the Haberfield/Ashfield area, it is likely that receivers would occasionally be subject to night-time period cumulative
impacts. This is predicted to exceed the NML by greater than 20 dBA within noise
catchment area (NCA) NCA01.
As above, receivers most likely to be affected by consecutive construction impacts from the M4 East and M4-M5 Link projects are:
- Receivers adjoining the Parramatta Road West civil and tunnel cite (C1b), Parramatta Road East civil site (C3b) and Haberfield civil site (C2b), between Walker Avenue and Chandos Street.
Cumulative construction noise impacts – Rozelle
Tunnelling works activities for the M4-M5 Link and the proposed future Western Harbour Tunnel project may be carried out simultaneously. Cumulative construction noise impacts may be apparent during outof-hours works periods where cumulative impacts are predicted to result in NML exceedances of up to 20 dBA during the
night-time period.
The Rozelle area would likely be subject to construction impacts from works associated with other infrastructure projects, including the under construction CBD and South East Light Rail Rozelle maintenance depot. The receivers most likely to be affected by consecutive construction impacts are:
- Receivers adjoining Lilyfield Road between Justin Concurrent construction impacts Consecutive construction impacts Street and Ryan Street (NCA16 and NCA19)
- Receivers adjoining Brenan Street between Starling Street and White Street (NCA15).
Cumulative construction noise impacts – St Peters
Given that tunnelling works activities may be carried out simultaneously at St Peters for
the New M5 and M4-M5 Link projects, cumulative construction noise impacts may be apparent during out-of-hours works periods where cumulative impacts are predicted to result in NML exceedances of up to 20 dBA during the night-time period.
Excluding short-term works such as pavement and utility works, receivers located within NCA48 and NCA49, which front Campbell Road, are predicted to experience up to 10 dBA exceedances of the project NMLs (during the night-time period) during construction of the M4-M5 Link project. Whilst the magnitude of the predicted exceedance is relatively
low, these impacts are predicted at receivers who would likely have been exposed to significant noise impacts from the New M5 project.
Potential management and mitigation measures
For concurrent cumulative construction noise impacts, mitigation (where relevant) could include scheduling use of high noise items of plant during less sensitive periods, increased height of construction hoarding, upgraded acoustic shed performance, noise monitoring, notification and respite offers, where appropriate.
In situations where consecutive long-term construction noise impacts occur, at-receiver noise mitigation could be considered, where appropriate, once options for a- source noise mitigation and management measures have been exhausted. Where it can be determined reasonable and feasible, the implementation of operational mitigation measures such as architectural treatments during construction may reduce cumulative impacts from concurrent construction activities, particularly for areas of overlapping works.
Operation
Potential cumulative operational noise impacts have been evaluated in the ‘Do Something Plus’ scenario (see Table 26-3) to represent the impacts of the future traffic from M4-M5 Link in conjunction with traffic from other major road projects.
Maps showing the location of receivers which are predicted to exceed the Roads and Maritime Noise Mitigation Guideline (2015b) (NMG) in the cumulative ‘Do Something Plus’ scenario are presented in Appendix J (Technical working paper: Noise and vibration).
The key findings of the cumulative assessment indicates that:
- The total number of receivers eligible for consideration of additional noise mitigation is predicted to decrease from 431 in the ‘Do Something’ scenario to 409 in the ‘Do Something Plus’ scenario which is typically due to traffic being removed from surface roads and instead using the M4-M5 Link tunnels
- There are more triggered receivers in the ‘Do Something Plus’ scenario in NCA21 (south of City West Link) compared to the ‘Do Something scenario’. This is due to cumulative traffic volumes of potential future projects anticipated to add traffic to the surface section of the project in this area
- There are less triggered receivers in the ‘Do Something Plus’ scenario in NCA25 (adjacent to Victoria Road and Lilyfield Road) compared to the ‘Do Something scenario’ due to a reduction in traffic for this section
- There are marginal differences between the scenarios elsewhere in the study area.
The majority of noise exceedances (in both the ‘Do Something’ and ‘Do Something Plus’ scenarios) are located in the vicinity of Victoria Road at Iron Cove and Victoria Road near Lilyfield Road and occur in part as a result of the demolition of existing buildings which act as a barrier to noise and as a result of widening of the road carriageway. A range of mitigation options are available to address exceedances from cumulative road traffic noise including use of low noise road pavement, noise barriers or architectural ‘at property’ treatments.
26.4.4 Human health
The results of the cumulative human health risk assessment discussed in this section is based on the outcomes of the air quality operational assessment, which has been derived from the traffic modelling. Construction fatigue is the main focus of the construction phase, while effects of emissions from the project as a result of the overall WestConnex program of works and other related projects are the focus of the operational phase.
Further details are provided in Chapter 11 (Human health risk) and Appendix K (Technical working paper: Human health risk assessment).
Construction
As described in section 26.3.1, construction fatigue relates to receivers that experience construction impacts from multiple projects over an extended period of time with few or no breaks between construction periods. Other impacts on health and wellbeing are associated with cumulative traffic impacts (including spoil vehicle movements, partial and/or complete closure of roads and active transport links, reduced street parking, and relocation of bus stops). Impacts on views and visual amenity from multiple concurrent or consecutive projects may also increase the levels of stress and anxiety experienced by community receptors.
Operation
This section provides a summary of the potential impacts to human health that may be experienced from air quality impacts under the cumulative modelling scenario for 2023 (opening year) and 2033, assuming the projects outlined in Table 26-1are operational.
In-tunnel air quality
While concentrations of pollutants from vehicle emissions are higher within the tunnel (compared with outside the tunnel), and with the completion of a number of tunnel projects (approved or proposed) there is the potential for exposures to occur within a network of tunnels over varying periods of time, depending on the journey. The assessment of potential exposures inside these tunnels, has indicated:
- Where windows are up and ventilation is on recirculation, exposure to nitrogen dioxide inside vehicles is expected to be below the current health based guidelines. In congested conditions inside the tunnels, it is not considered likely that significant adverse health effects would occur. Placing ventilation on recirculation with windows closed is also expected to minimise exposures to particulates during travel through the tunnels
- For motorcyclists, where there is no opportunity to minimise exposures through the use of ventilation, there is the potential for higher levels of exposure to NO2 and particulates. These exposures, under normal conditions, are not expected to result in adverse health effects. When the tunnels are congested it is expected that motorcyclists would spend less time in the tunnels than passenger vehicles and trucks (due to lane filtering), limiting the duration of exposure and the potential for adverse health effects
- For individuals who regularly use tunnels for commuting or as part of their employment there is the potential for repeated exposures to higher levels of NO2 and particulates during the day.
While these exposures are not likely to be additive, in terms of potential health effects, it is important that these road users utilise ventilation on recirculation whenever they are using the tunnels. Where advice to place ventilation on recirculation when using the tunnel or the proposed network of tunnels is followed, it is not expected to result in carbon dioxide levels inside the vehicle that may adversely affect driver safety. However, where Roads and Maritime provides specific advice to drivers entering road tunnels to put ventilation on recirculation, it is recommended that further advice is provided that recirculation should be switched off at some point after using the tunnel network and not left on for an extended period of time.
Ambient air quality
The human health risk assessment evaluated the principal pollutants from the air quality assessment and determined that these pollutants, including VOCs, PAHs, CO and NO2, were not associated with any acute or chronic risk issues in the local community, when considered cumulatively with other projects. The cumulative health risk assessment concludes that predicted changes for ground level particulate matter (PM10 and PM2.5) due to the ‘cumulative’ scenario (compared to the ‘with project’ scenario) are unlikely to be measureable.
For receptors located at elevated heights, such as in high rise buildings, the assessment concluded that at a height of 10 metres the maximum predicted change in PM2.5 in the ‘cumulative’ scenario (compared to the ‘with project’ scenario) is lower than at ground level.
At a height of 30 metres, the maximum predicted change in PM2.5 in the ‘cumulative’ scenario (compared to the ‘with project’ scenario) is significantly greater than at a height of 10 metres. Predicted levels at this height are considered unacceptable for future high-rise development in the vicinity. The impacts identified at 30 metres above ground are localised and close to the ventilation outlets, with the maximum increases more specifically located adjacent to the Campbell Road ventilation facility at the St Peters interchange. Conversely, at the closest existing residential area, the maximum increase at a height or 30 metres is considered to result in a risk which is tolerable/acceptable.
Planning controls (including re-zonings) for land in the vicinity of the proposed Campbell Road ventilation facility at St Peters interchange are required to ensure future developments at heights 30 metres or higher are not adversely impacted by the ventilation outlets. Development of planning controls would be supported by detailed modelling addressing all relevant pollutants and averaging periods.
Mitigation and management measures for cumulative human health impacts are the same for project impacts and are outlined in Chapter 11 (Human health risk).
26.4.5 Urban design and visual amenity
The urban design and visual impact cumulative assessment focuses on the changes to the landscape character and visual amenity that result from the combined effects of the WestConnex projects and other relevant projects as outlined in Table 26-1.. This is summarised below and is supported by further detail in Appendix O (Technical working paper: Landscape and visual impact).
M4 East
The majority of the works associated with the M4 East project at Haberfield and Ashfield would either be completed or close to completion when the M4-M5 Link construction period commences. The overlapping projects would result in a large number of nearby residents in Haberfield and Ashfield being subject to a further four to five years of motorway construction work within their neighbourhood. mThis would also affect motorists who regularly travel through the area. This would result in a high cumulative visual amenity impact on affected Haberfield and Ashfield residents due to the continued presence of visible construction facilities and construction activities over this period.
New M5
The majority of the works associated with the New M5 project at St Peters would be almost complete when the M4-M5 Link construction period commences. The completed New M5 works would provide substantial levels of amenity for local residents within the vicinity of the construction site, notwithstanding the early stage of landscape development. New motorway infrastructure including the interchange, ventilation outlets, motorway operations complex and associated infrastructure would be visible together with the open space area along the south side of Campbell Road and the extensive landscape setting.
The number of sensitive residential receptors affected by the project is considered likely to be relatively small. However, for this small group of residents, the project would result in a further prolonged period of construction. The project is also likely to extend impacts on users of Sydney Park and motorists who regularly drive through this area.
Rozelle Rail Yards site management works
Once the site management works are completed, the landscape character of the site would be altered through the removal of vegetation, structures and redundant rail infrastructure, and subsequent increase in the extent of open land and a largely vacant site. While the site management works are unlikely to result in a significant impact, there is a potential for cumulative visual impacts when considered in conjunction with the M4-M5 Link project because of the change to the existing environment. Once the M4-M5 Link is completed, part of the site will be used for operational infrastructure associated with the motorway and the balance of the land will be made available for use
as open space and landscaping.
Western Harbour Tunnel
As limited information is available on the project, for the purposes of this EIS, it is assumed that the construction of the Western Harbour Tunnel will involve surface works at the Rozelle Rail Yards during construction of the M4-M5 Link and beyond 2023.
This suggests that visual impacts associated mwith construction activities from the M4-M5 Link would occur concurrently and consecutively. This would result in the proposed open space area at Rozelle Rail Yards being delivered in stages – the first stage in late 2023 and the next stage some time post 2023 after completion of the Western Harbour Tunnel construction. This would extend the visual impacts associated with construction for a longer duration at Rozelle.
CSELR – Rozelle Maintenance Depot
The CSELR Rozelle maintenance depot at the western end of the Rozelle Rail Yards may result in cumulative impacts when considered in conjunction with the M4-M5 Link project. Removal of vegetation, which has been undertaken as part of the CSELR project, has provided unfiltered views at some locations to the construction areas and could lead to more prominent views to parts of the M4- M5 Link project for sensitive receptors such as the residences along Lilyfield Road.
The Bays Precinct Transformation
Due to The Bays Precinct only being in its early strategic planning stages, no detailed assessment of landscape and visual impacts has been undertaken. The sensitivity of The Bays Precinct to change can be considered low due to the existing poor amenity provided by the current industrial and port related land uses and in some areas, derelict, built form.
The M4-M5 Link project would create a significant area of open space and improved active transport connectivity which would be available to service people working, living and visiting The Bays Precinct. There is an opportunity for integration between the sites to ensure a balanced outcome from a visual amenity, active transport and heritage perspective. Roads and Maritime has been working with UrbanGrowth NSW to ensure their plans for The Bays Precinct have been considered in relation to the design of the Rozelle interchange.
26.4.6 Social and economic
This summary of cumulative social and economic impacts is supported by the findings in Appendix P (Technical working paper: Social and economic). The focus of the cumulative social and economic impacts associated with transport and infrastructure projects include:
- Construction fatigue, entailing extended periods of construction, impacting local amenity, disruption to traffic and pedestrian networks
- Incremental loss or severance of open space
- Impact on property value or rent return due to ongoing project works as a result of multiple projects
- Economic effects, including changes to business operation and revenues
- Construction traffic from multiple projects placing additional pressure on road networks and parking capacity.
The assessment of cumulative impacts includes those activities that may overlap with the timing of the construction of the M4-M5 Link project, or have recently been completed. These are outlined in Table 26-1..
When completed, WestConnex is predicted to deliver beneficial cumulative impacts to the community, including increased travel speeds and reduced travel time through local streets, improved connectivity and reliability and opportunities for urban renewal. WestConnex, while delivering longer-term benefits, is likely to result in some adverse social and economic cumulative impacts for the community during the construction phases of the various component projects. The health effects of construction fatigue
through annoyance, stress and anxiety have been covered in the health risk assessment section.
At Haberfield and Ashfield, the overlap between the M4 East and M4-M5 Link projects is likely to result in continuous construction activity for around seven years, which is expected to contribute further to traffic delays for customers and staff of businesses in the locality, in addition to extended periods of amenity impacts due to increases in noise and dust levels and changes in visual amenity.
At St Peters, residents and businesses located in areas of overlap with the New M5 project and the M4-M5 Link, could experience cumulative amenity impacts due to increases in traffic, changes in traffic patterns, parking, construction noise and vibration, and changes in visual amenity due to new infrastructure associated with these projects.
Coordination between and the projects in the planning of possible disruptions would assist in minimising potential cumulative impacts.
Positive cumulative impacts to local businesses and the economy would likely result from the concurrent construction activity associated with the WestConnex program of works and related projects such as the proposed future Sydney Gateway, Western Harbour Tunnel and Beaches Link and F6 Extension projects, which is likely to intensify employment and stimulus impacts. The demand for labour for major projects such as WestConnex and other similar projects in the area would increase employment opportunities for local residents. There is potential for wages to increase due to high demand for construction workers and opportunities for local businesses to supply goods or services for construction of these projects. Business turnover is also likely to increase due to demand.
As a result, there would be cumulative benefits of the projects, resulting in significant increases in travel speeds through the local road network, a reduction in average travel times and improved business and freight connectivity.
26.4.7 Non-Aboriginal heritage
This assessment of the potential cumulative impacts is supported by Appendix U (Technical working paper: Non-Aboriginal heritage).
The projects included in this assessment and their overall heritage impact rating are presented inTable 26-1..
Table 26-7 Overall heritage impact ratings for the WestConnex projects
The WestConnex program of works as a whole has potentially wide reaching impacts on the urban fabric of greater metropolitan Sydney, including on items and areas of heritage significance. The overall cumulative impacts of the entire WestConnex program of works to date can be described as major and irreversible given the scale of the project, primarily the impacts to the Haberfield area heritage conservation area from the M4 East project.
The site management works and M4-M5 Link project at the Rozelle Rail Yards would permanently remove evidence of the rail infrastructure heritage and character of the site. However, the project would reuse and incorporate heritage elements in the urban design and landscape plan for Rozelle, acknowledging heritage themes and interpretation of area.
The heritage fabric, features and values of the items and areas in which these projects are located are being subjected to increased development pressures. While these projects will be transformative and place-making, they will lead to impacts on heritage items and the associated cultural and social values that they provide.
26.4.8 Biodiversity
The cumulative impact assessment for biodiversity focuses on the identification of conservation significant species found within the broader study areas of each of the relevant WestConnex and related projects and also assesses the extent to which their habitat has been removed. The assessment only examines the species which are in common across two or more projects, these are the threatened Grey-headed Flying Fox, the Eastern Bentwing-bat and the Yellow-bellied Sheathtailbat.
A detailed assessment of the potential construction and operational impact of the M4-M5 Link is provided in Chapter 18 (Biodiversity) and is supported by Appendix S (Technical working paper: Biodiversity).
Table 26-8 provides a summary of the impacts to the biodiversity features as a result of the combined relevant projects examined as part of this cumulative assessment. While very little native vegetation would be removed collectively, the removal of exotic and planted vegetation that species use for foraging has been identified as a contributor to the overall impact of the WestConnex program of works.
Table 26-8 Summary of cumulative impacts Project Area (hectares)
The impacts of the WestConnex program of works and other related projects have been assessed and consistent management measures have been identified. In total, approximately 3.86 hectares of native vegetation would be impacted by the WestConnex program of works, which is not significant in the context of existing native vegetation across the Sydney Basin. No native vegetation is to be removed as part of the M4-M5 Link project.
Around 50.18 hectares of exotic and planted vegetation (mapped as ‘urban exotic and native cover’) would be removed and represents potential foraging habitat for the Grey-headed Flying-fox. A total of 4.49 hectares of urban exotic and native cover is to be removed by the M4-M5 Link project and a further 7.12 hectares is to be removed by the Rozelle Rail Yards site management works.
Some 38.67 hectares of the native vegetation and urban and exotic vegetation to be removed has also been identified as potential foraging habitat for the Eastern Bentwing-bat and Yellow-bellied Sheathtail-bat.
The cumulative impacts to Grey-headed Flying-fox and the threatened microbats would not result in a significant impact. No camps or breeding sites would be impacted and the removal of potential feed trees and foraging habitat would be negligible in the context of existing available foraging habitat for these species. Offset for individual trees would be integrated into landscape plans for the individual projects, and would provide foraging habitat for species such as the Grey-headed Flying-fox and microbats.
26.4.9 Soil and water quality
The cumulative impacts assessment for soil and water quality focuses on the potential for contaminated soil and water to cross project boundaries.. Cumulative impacts of this nature are unlikely to occur during the operations phase or on projects that are widely separated. This section therefore addresses the construction phase for projects that overlap or are in close proximity to each other.
Review of EIS documents for the various approved projects located in proximity to the M4-M5 Link project, including M4 East and New M5 indicate that the disturbance and management of contaminated soil, fill, sediment, surface water and groundwater as a result of construction and operational activities are unlikely to have a more significant impact on ecological and human health receptors or sensitive environments than they would if undertaken as discrete projects, provided the proposed management and mitigation measures documented in the respective EISs are implemented, maintained and monitored.
There are minimal adverse cumulative contamination impacts anticipated to occur as part of the construction or operation of the M4-M5 Link project. Risks to human health and the environment would be mitigated through implementation of management measures outlined in Chapter 11 (Human health risk) and Appendix K (Technical working paper: Human health risk assessment).
The construction and operation of the M4-M5 Link project is not anticipated to create additional soil or groundwater contamination to that already identified within the project footprint as a result of historical land use activities. The appropriate management of contamination and waste materials disturbed during the construction phase of the project would likely result in an overall improvement in the condition of the land at project completion. The project would incorporate remediation and
management of existing contamination as part of the construction phase, and to make the land suitable for the proposed final land use. Site suitability for the proposed land use(s) would be determined by an independent NSW EPA accredited site auditor engaged for the project.
Further assessment of cumulative impacts associated with contamination and groundwater contamination are discussed in Appendix R of the EIS (Technical working paper: Contamination) and Appendix T of the EIS (Technical working paper: Groundwater).
26.4.10 Surface water flooding and drainage
This cumulative assessment focusses on the capacity of the drainage network to accommodate the M4-M5 Link project in combination with other relevant projects. A detailed assessment of the potential construction and operational impact of the M4-M5 Link is provided in Chapter 17 (Flooding and drainage) and is supported by Appendix Q (Technical working paper: Surface water and flooding).
WestConnex projects
Table 26-14 provides a summary of the findings of the cumulative impact assessment for the M4-M5 Link project in relation to surface water and flooding in the context of other WestConnex projects.
Table 26-9 Summary of impacts on surface water and flooding – WestConnex program of works
M4 Widening and King Georges Road Interchange Upgrade
- No surface water receptors in common with the M4-M5 Link project therefore no direct cumulative impacts on surface water bodies or water quality
- Potential for cumulative water quality impacts on downstream sensitive environments such as the Parramatta River Estuary, Cooks River and Botany Bay
- No common surface catchments with the M4-M5 Link project there no potential cumulative flood impacts are anticipated.
Negligible impact
M4 East
- Potential cumulative surface water quality impacts could impact on the one common receptor, Dobroyd Canal (Iron Cove Creek) and downstream environments (including Iron Cove and the Parramatta River Estuary)
- Impacts are associated with increased pollutant loading to Dobroyd Canal (Iron Cove Creek) from stormwater runoff or the discharge of poorly treated tunnel water
- The M4-M5 Link connection to the Wattle Street interchange will not alter the surface layout or levels. Accordingly, there are no cumulative flooding impacts expected at the Wattle Street interchange.
Negligible impact
New M5
- Potential cumulative surface water quality impacts could impact on one common receptor the M4-M5 Link ie. Alexandra Canal as well as downstream sensitive environments such as the Cooks River and Botany Bay
- The M4-M5 Link connection to the St Peters interchange will not alter the surface layout or levels. Accordingly, there are no cumulative flooding impacts expected at the St Peters interchange
- Slight increase in tunnel wastewater discharging from the Arncilffe operational water treatment plant to the Cooks River due to the portion of M4-M5 Link tunnel drainage draining to the New M5 system.
Negligible impact
Other relevant projects
Cumulative impacts considered for other approved or proposed projects proposed in the vicinity of the M4-M5 Link project footprint are summarised in Table 26-10.
Table 26-10 Summary of impacts on surface water and flooding – other relevant projects
CBD and South East Light Rail Rozelle maintenance depot
- Surface water from the depot will be discharged to the Rozelle Rail Yards as surface flow
Low impact \
Sydney Metro City and Southwest
- Waterloo Station, part of the Sydney Metro project, is located within the Alexandra Canal catchment and could therefore impact on Alexandra Canal and downstream sensitive environments (Cooks River and Botany Bay)
- The aboveground station infrastructure would have a negligible impact on the existing surface hydrology or existing flood behaviour.
Negligible impact
Whites Creek naturalisation
- Potential sedimentation of Whites Creek during earthworks
- Flooding impacts during operation are not expected.
Low impact
The approved WestConnex component projects are considered unlikely to have a significant cumulative impact on receiving water receptors or sensitive environments provided the proposed management measures are implemented, maintained and monitored. There are minor adverse cumulative surface water quality or flooding impacts anticipated and the residual risk to common receptors and sensitive environments downstream would be low.
The flood modelling for the M4-M5 Link included the anticipated surface discharge from the CSELR Rozelle maintenance depot adjacent to the Rozelle Rail Yards. The modelling results were fed into the concept design for the Rozelle interchange, which accommodates flows across the site into Rozelle Bay. The detailed design for M4-M5 Link would need to consider the final design of the Rozelle maintenance depot drainage system further.
The Sydney Metro City and Southwest project, specifically the proposed Waterloo Station, would have negligible surface water impacts with the implementation of appropriate measures, therefore there are no anticipated cumulative water quality or flooding impacts with the M4-M5 Link.
The M4-M5 Link project works at Whites Creek together with the proposed naturalisation works by Sydney Water could have potential impacts on flooding and sedimentation of the channel, however this is expected to be a low impact, as suitable measures will be put in place during detailed design and construction.
26.4.11 Groundwater
The potential cumulative impact on groundwater focuses on impacts related to the quality and quantity of the groundwater resource and how it can affect groundwater dependent ecosystems. This typically arises from groundwater drawdown which as it draws in water from surrounding locations, it can have a potential effect on groundwater quality. This is discussed in detail in Appendix T
(Technical working paper: Groundwater).
This cumulative impact assessment quantitatively assesses (through modelling) the potential impacts of other WestConnex tunnel projects (ie the M4 East and New M5 projects) and qualitatively assesses the potential impacts of other relevant projects such as the Sydney Metro City and Southwest, as outlined below. The construction and operational groundwater impacts of the M4-M5 Link are described in Chapter 19 (Groundwater).
WestConnex projects
During construction, cumulative impacts on groundwater would be greatest at either end of the mainline tunnel alignment where the M4-M5 Link tunnels would overlap with the tunnels for the M4 East tunnels at the Wattle Street interchange and with the New M5 tunnels at the St Peters interchange.
Once all three of these WestConnex tunnel projects are operational, groundwater drawdown due to the cumulative impact of the three tunnel projects is not expected to be greater than in any one section of the overall project footprint. The tunnels and associated lining for each project would be designed and constructed to comply with the groundwater inflow criterion of one litre per second per kilometre for any kilometre length of tunnel. Consequently, the groundwater inflows along the tunnels would vary within a known range. A comprehensive groundwater monitoring program would be
required for each project to confirm that the actual inflows do not exceed the criterion and drawdown does not exceed predictions.
Long term cumulative groundwater tunnel inflows due to the WestConnex tunnel projects may cause groundwater salinity to increase due to surface water from tidal reaches being drawn into or towards the tunnels. Initially, the saline water would be a small fraction of total tunnel ingress but this is expected to increase over time as water is drawn from further afield, although it is expected to always be a minor component of total inflow volume.
Other relevant projects
The Sydney Metro City and Southwest rail tunnels are to be constructed as undrained (tanked) tunnels that would cross the M4-M5 Link project alignment near St Peters. As the twin Sydney Metro tunnels are to be constructed as tanked tunnels, there will be negligible impacts on groundwater drawdown. The station boxes are to be constructed and operated as drained shafts and will extract groundwater from the local hydrogeological regime over time. The closest drained structure is proposed at Marrickville Station which is some distance to the west of the M4-M5 Link, and as such is
considered unlikely to have significant cumulative impacts on groundwater drawdown.
There is potential for the concrete lined tunnels of the Sydney Metro project to create a partial hydraulic barrier to groundwater flow, however the risk is considered low since the tunnels are constructed below the water table.
The Western Harbour Tunnel project has potential to have cumulative groundwater impacts with the M4-M5 Link project in the Rozelle area. At this stage only limited information is available about the proposed design and construction methodology for the Western Harbour Tunnel project and as a result no meaningful analysis of impacts is possible at this time. Cumulative groundwater impacts should be addressed in the future as part of the EIS for the Western Harbour Tunnel project.
26.4.12 Aboriginal heritage
Potential cumulative impacts on Aboriginal heritage relates to the extent and number of registered AHIMS sites likely to be disturbed by the construction activities of a number of projects, including the M4-M5 Link, as outlined below. Further details on these potential cumulative impacts are provided in Appendix V (Technical working paper: Aboriginal heritage).
Potential impacts of the M4-M5 Link on Aboriginal heritage are summarised in Chapter 21 (Aboriginal heritage). The findings of the assessment indicated no significant impacts on Aboriginal heritage items.
None of the approved component projects of the WestConnex program of works have any significant impact on Aboriginal heritage, therefore there are no cumulative impacts associated with these projects and the M4-M5 Link. No other projects were identified that could result in potential cumulative impacts on Aboriginal heritage.
26.5 Management of cumulative impacts
Construction impacts would be minimised through further consideration during detailed design and construction planning, application of appropriate management and mitigation measures, and consultation with affected residents and stakeholders. The construction strategy for the project (and the broader WestConnex program of works) focuses on balancing the need for construction to occur in a safe and efficient manner while managing constructability constraints and minimising cumulative impacts on the community, environment, road users and the surrounding road network.
The design of the project has carefully considered minimising construction fatigue as far as practical. The intent is to reduce the overall cumulative or consecutive impacts on the community over a longer period.
Each of the study disciplines presented in this EIS have identified site specific management measures to reduce the potential impact to acceptable levels. This cumulative assessment has been undertaken assuming that those management measures are implemented at the appropriate time.
Assuming that the practical mitigation measures for each key factor are already in place, the cumulative mitigation focussed on a broader level, focussing on the opportunities around inter-project coordination and communication with stakeholders. Mitigation and management measures for the cumulative scenario are constrained by only being able to be applied to the M4-M5 Link project and not those others that have already been approved.
Table 26-11 presents a summary of mitigation and management measures aimed at facilitating the reduction of cumulative impacts from the M4-M5 Link project and the other relevant projects included in this assessment.
Table 26-11 Proposed mitigation and management measures for cumulative impacts
Social and economic; traffic and transport; air quality; noise and vibration
Ongoing construction impacts on the local community throughout the construction phase of the M4-M5 Link
- The effective management of cumulative impacts on the affected community requires oversight and direction from one overarching body such as a government department/agency or local council
- Multi-party engagement and cooperation is needed to ensure all contributors to impacts are working together to minimise the effects or enhance the benefits of multiple projects occurring concurrently or consecutively
- Communication strategies across the various projects should be managed to be consistent in their messaging to the community to avoid confusion.